Reports 1-9 of 9 Clear search Modify search
AdV-SAT (Suspension control upgrade)
Boschi, Dattilo, Gennai, Nenci, Piendibene, Ruggi - 17:20 Tuesday 09 April 2024 (63855) Print this report
Summary of tests performed on Sa_PR

In order to debug the periodic glitches on PR horizontal accelerometers - that introduce a rotation of the F0 along ty and generate interferometer unlocks - a series of tests have been performed on Sa_PR control system during the last weeks:

  • The sensing element of the accelerometers were re-centered.
  • In order to identify possible communication problems on RapidIO bus, 'keep sample' has been enabled on coil driver DSP board code.
  • In order to identify possible issues due to the distribution box, channels used by the in-air cables were swapped: horizontal accelerometers previously connected to channels 1,2,3 were moved to channels 4,5,6 and vertical accelerometers from #4,5 have been moved to #1,2.
  • In order to identify possible issues due to the dedicated DSP boards, horizontal accelerometers have been connected to the DSP board previously connected to the vertical ones and viceversa. This operation has required a re-design of the controllers.
  • In order to identify possible issues due to cabling, mechanical action on in-air cables was performed. Even though this test introduced similar glitches in the signals, they were longer respect to the ones causing the unlocks. Moreover similar actions on the accelerometer cabling of other towers produced similar results in ther respective signals.

Unfortunately all these were inconclusive. Even though the third test did not produce any change, we decided in any case to replace the distribution box this morning. Primary, secondary and feedback coils have been measured as well.

Comments to this report:
ruggi - 10:35 Wednesday 10 April 2024 (63912) Print this report

Waiting for new ideas about the origin of PR trips, a software mitigation of the problem has been implemented yesterday. The method is based on a few systematic characteristics of the trips:

1) the trip is anticipated by a fast glitch on the accelerometers;

2) the IP displacement along Z, which is the cause of unlock, is proportional to the IP rotation TY. This is a clean signal where one can read quite early the direction of the trip;

3) the trip can be well reproduced by adding a step to the accelerometers in a certain combination. The accordance is very good: very likely the trip is produced by a disturbance which adds a constant to the three signals. In principle, a mechanical disturbance (a tilt) can produce such an a effect on an accelerometer, but a common tilt on the structure where the three accelerometer are placed would produce basically a translation of IP. The large component of rotation seems definitely associated to an electrical disturbance on the sensors.

The fast glitch can be used as a trigger for producing an artificial step to be sent to the accelerometers. The TY signal can be used to know, in less than 1 second, the sign of the step needed to generate an opposite trip. In order to do that, the trigger is used to generate a time window (fig 1), during which TY is compared to a positive and a negative threshold. When a threshold is crossed, the appropriate step is sent. The step generates a trip only in Z combination, the only one which actually needs to be compensated. TY is not compensated, because interacting with the witness could produce a second dangerous crossing of the threshold.

This night two trips occurred: a large one (fig 2) and a small one (fig 3). Comparing the first to a similar past trip, one can see that the amplitude of the Z component has been reduced enough to avoid the unlock. Also the small one did not produce an unlock, but the figure shows that the compensation produced a dangerous trip in the opposite direction (over-compensation). The amplitude of the step has been defined in order to stay about in the middle between large and small trips, but we cannot exclude that a small harmless trip could be compensated so much to produce an unlock.

On this purpose, an improvement of the feed-forward can be studied, because the delay between the fast glitch and the TY crossing of a threshold contains the information to define a good amplitude of the step. Maybe it can be implemented after acquiring some statistics on the compensated trips.

Images attached to this comment
ruggi - 16:37 Wednesday 10 April 2024 (63922) Print this report

A bug in the feed-forward code has been found and fixed. It was preventing the application of the step in some unlucky situation: that is the reason why the unlock has not been prevented during the latest PR trip.

mwas - 18:01 Wednesday 10 April 2024 (63924) Print this report

Figure 1 and 2. I have looked at two example of the PR F0 accelerometer glitches in the raw_full data that are sampled at 10kHz. The glitch time scale is ~1ms.

The glitch is also visible in the COIL channels as pointed out by Didier this morning. But this seems rather like a consequences, as it happens a few ms later and has a longer time scale by a factor few. What are these COIL channels? Are these corrections of a feedback loop, and if yes what is its bandwidth?

The glitch is also visible in the V1 vertical accelerometer, but it has a different shape. It looks like a step. It is not present in the V2 vertical accelerometer. Is there something that is common between the H1, H2, H3 and V1 accelerometer, but different for the V2 accelerometer? For example is there a cable connector common to H1, H2, H3 and V1, but different for V2?

Figure 3 shows that the horizontal feedback of the accelerometer looks like a step response, so it might be that the horizontal accelerometer error signal doesn't look like a step, as the step is removed by the feedback loop, while for the vertical accelerometer it is not removed by the feedback loop keeping the proof mass centered inside the accelerometer.

Images attached to this comment
Boschi, Ruggi - 14:26 Tuesday 16 April 2024 (63984) Print this report

This morning LVDT modulation frequency of the horizontal accelerometers has been changed (from 49.5 to 48.3 kHz). The demodulation phases has been adapted, the sensing elements have been re-centered, the TFs re-measured and the controllers re-estimated. Horizontal inertial damping gains has been re-measured as well and changed accordingly.

ruggi - 20:21 Tuesday 16 April 2024 (63989) Print this report

So far we had just one fast gitch on the three PR ACC, not too different from the usual ones, but it was not followed by any trip. Let's wait for the next.

Images attached to this comment
ruggi - 9:36 Wednesday 17 April 2024 (63994) Print this report

After the modification of PR ACC H modulation frequency, we had 3 fast glitches - the usual rate observed recently - but no one triggered a trip. This is a good news: it seems that the problem has been fixed. To be noticed that the trips disappeared also from the vertical loop, but PR ACC V modulation frequency was not touched.

Images attached to this comment
dattilo - 12:57 Wednesday 17 April 2024 (63999) Print this report
the Dbox serial numbers are:
#10 (the pre-existing one)
#8 (the one installed on Tuesday 9th)
On-call intervention (General)
Boschi, Piendibene - 17:22 Tuesday 23 January 2024 (63067) Print this report
Comment to On-call intervention (63035)

Boot image version of BPC DSP boards has been updated to the same version currently used on Sc_NI crate (see entry #62523).

AdV-SAT (Suspension control upgrade)
Boschi, Gkaitatzis, Passuello, Piendibene, Ruggi - 18:06 Wednesday 08 November 2023 (62399) Print this report
Overall Suspension System Recovery

Due to the power outages on Friday, first at MC building - that was initially recovered on the same morning - and then in the central building (see entries #62359 and #62360) the entire suspension control system (SAT+PAY+INJ+DET) and the BPC had to be kept off over the weekend. The full recovery started on Monday morning. Three main issues were found: 

  • A DSP board connected to MC PSDi (serial #43168) was not able to boot. Its EEPROM was re-programmed and the board was re-installed.
  • SR smart PDU failed to restart and its firmware has to be re-flashed, in order to power up the DSP crates.
  • BS DSP connected to vertical accelerometers (serial #41032) went in a frozen state quickly after boot: GPS time was wrong and all acquired signals were constant. It has to be replaced with a spare (serial #43154). For that reason the accelerometer controllers have to be re-calculated and the vertical inertial damping gains re-estimated.

Now all hardware, control loops, DAQ and GC communication of BPC, BS, PR, NE, WE, NI, WI, IB, MC, OB are working properly except for BS vertical inertial damping. 

AdV-SAT (Suspension control upgrade)
Boschi, Gennai, Piendibene, Sposito - 16:46 Tuesday 06 June 2023 (60464) Print this report
Comment to Suspension system complete recovery (60262)

Sa_SR crate that was partially damaged by the blackout has been replaced with a spare. Now DSP master board (serial #43147) is back in slot #1 and MCH previous configuration has been restored in order to properly propagate the timing signals to the other DSPs. However, probably due to minor mechanical incompatibilities in the MicroTCA connectors, p4 coil driver board (serial #42074), connected to F0, has to be moved from slot #5 to slot #6: DSP code has been changed accordingly.  All SR loops are now closed.

AdV-SAT (Suspension control upgrade)
Boschi, Gennai, Gkaitatzis, Majorana, Piendibene, Ruggi - 17:07 Sunday 21 May 2023 (60262) Print this report
Suspension system complete recovery

The failure of the electric system on last Wednesday has required a complete recovery of the control electronics of all suspensions. At the start of the intervention on Thursday morning, all crates were ON, expect for SR ones where the smart PDU was frozen in an unknown state that required a reconfiguration of the device. Three DSP boards were damaged and has to be replaced with spares: 

  • Sa_SR master board (serial #43131), connected to bottom ring LVDTs, was unreachable on the network and has been replaced with DSP #43147;
  • Sc_BS PSD board (serial #42110), connected to marionette transversal optical lever, was unreachable on the network and has been replaced with DSP #45270;
  • Sa_PR board (serial #41026), connected to both F0 horizontal and vertical LVDTs, was malfunctioning generating corrupted signals, probably due to a damaged ADC or DAC. It has been replaced with spare with serial #41049. 

Moreover the SR top crate was partially damaged by the blackout: the slot #1 that hosts the master board, connected to both DAQ and timing box, was not working properly anymore. In particular MCH was not capable of powering any DSP inserted in that slot (in order to exclude problems on the MCH itself, bottom and top MCHs were temporarily exchanged). For this reason the spare LVDT board has to be installed on slot #7, action that required a reconfiguration of the MCH in order to properly propagate the timing signals to the other DSPs.

After the hardware interventions all crates of all towers has to be resynchronized with timing for proper DAQ transmission and all controls loops has to be verified and closed. The system was fully operational on Friday evening as reported by the on-shift operator (entry #60260).

Comments to this report:
Boschi, Gennai, Piendibene, Sposito - 16:46 Tuesday 06 June 2023 (60464) Print this report

Sa_SR crate that was partially damaged by the blackout has been replaced with a spare. Now DSP master board (serial #43147) is back in slot #1 and MCH previous configuration has been restored in order to properly propagate the timing signals to the other DSPs. However, probably due to minor mechanical incompatibilities in the MicroTCA connectors, p4 coil driver board (serial #42074), connected to F0, has to be moved from slot #5 to slot #6: DSP code has been changed accordingly.  All SR loops are now closed.

AdV-SAT (Suspension control upgrade)
Boschi, Piendibene - 16:32 Wednesday 29 March 2023 (59505) Print this report
Board Replacement at WE

As mentioned in entry #59501, this morning at around 8:30 UTC, during some tests on PDU new supervisor, the WE top crate was incidentally turned off. This unintended operation unfortunately caused a problem on the DSP board connected to the F0 vertical accelerometers (serial #43154). The board has been replaced by the one previously connected to MC vertical accelerometers (serial #43158) before the installation of the current board setup (see entry #59222). New controllers have been estimated and implemented. A measurement of the vertical inertial damping control gains is now required before closing the loop.

AdV-SAT (Suspension control upgrade)
Boschi, Dattilo, Montanari, Piendibene, Trozzo - 12:55 Wednesday 22 March 2023 (59375) Print this report
Activities on MC Accelerometers

Yesterday in order to enable inertial damping control on both horizontal and vertical DOFs of the MC suspension, after the issue described in entry #59222, the accelerometer DSP boards have been replaced with an LVDT (serial #43129) and Coil Driver p4 (serial #42119) set. This intervention required the production and installation of a dedicated distribution box based on the design of the one installed at SR. Due to the DSP board configuration changes, for all the 5 accelerometers, the demodulation phases of the LVDTs and the transfer functions have to be re-measured. Moreover the LQG controllers have to be re-designed and implemented in the CD board. This latter task has been completed this morning. 

Comments to this report:
Ruggi, Trozzo - 17:39 Wednesday 22 March 2023 (59382) Print this report

The vertical and horizontal Inertial Damping (ID) loops are back in operation.

AdV-SVS (Installation)
S. Gkaitatzis, M. Piendibene, A. Gennai, F. Sorrentino - 13:28 Monday 21 December 2020 (50291) Print this report
SVS Actuators Deployment (continues)

The following devices are currently available under ESQB1:

DEVICE SN CONNECTION
MFF101 37002313 PC HUB
KIM101 97100545 HUB RIGHT
KIM101 97100527 HUB RIGHT
KIM101 97100521 HUB RIGHT
KIM101 97100541 EXT PORT HUB RIGHT
KIM101 97100506 HUB LEFT
KIM101 97100513 HUB LEFT
KIM101 97100560 HUB LEFT
KIM101 97100542 EXT PORT HUB LEFT

 

AdV-SVS (Installation)
S. Gkaitatzis, M. Piendibene, A. Gennai, F. Sorrentino - 11:05 Tuesday 15 December 2020 (50223) Print this report
SVS Actuators Deployment
Yesterday we started deployment of control electronics for ESQB1 motorized optics. Devices will be placed under the optical bench. Work will continue next Friday.
Images attached to this report
Search Help
×

Warning

×